Applied Digital — 2026Q4 earnings

reported 2026-10-07

EPS -$0.01 vs -$0.30 est — beat

Revenue $341.9M vs $124.6M est — beat

next session +0.2% (close 2026-10-07 → 2026-10-08)

Financial flow diagram

A verified financial-flow breakdown is not yet available for this report.

Source

8-K filing ↗

Summary

Applied Digital's fiscal first quarter (reported October 7, 2026) beat on both lines, but the revenue beat reads differently once its make-up is visible. On the call the CFO split HPC hosting revenue of $262.6 million into $183.5 million of tenant fit-out services, $65.8 million of base rent and $13.3 million of tenant recoveries, and fit-out services carried $176.1 million of cost. Most of the quarter's revenue was therefore low-margin fit-out work for tenants, not recurring rent. The rent base is earlier in its ramp: 250 MW was live at Polaris Forge 1 after October 1, the company expects 300 MW across North Dakota by the end of calendar 2026, and management expects to place over 600 megawatts into service over the next 12 months. The EPS beat is on the adjusted line, a loss of $0.01 per diluted share. GAAP shows a loss of $0.76 per share, including a $67.5 million non-cash mark on the Babcock & Wilcox position, and the non-GAAP figures exclude ChronoScale. Our read: the quarter confirms delivery on schedule and cheaper funding, with the last Polaris Forge 1 tranche at 7% against 9.25% on the first notes. The case still rests on two things ahead: financing Polaris Forge 3 and Delta Forge 1 and 2, and turning the roughly $36 billion of contracted revenue into rent as the buildings come online.

Earnings call

Earnings call webcast ↗

Transcript ↗

Review

From the report

Both lines beat on revenue of $341.9 million, up 322%, and an adjusted net loss of $0.01 per diluted share. The GAAP picture is a net loss attributable to common stockholders of $0.76 per share, and the non-GAAP measures exclude ChronoScale. The operating news is capacity and funding: 250 MW live at Polaris Forge 1, 300 MW expected across the North Dakota campuses by the end of calendar 2026, the 210 MW Delta Forge 2 lease, $1.59 billion of 7.000% notes, and new power options in Finland and North Dakota.

  • Revenue was $341.9 million, up 322% from the prior-year quarter. show quote
    “Revenues: $341.9 million, up 322% from the prior year comparable period”
    source ↗
  • GAAP and adjusted results diverge sharply. Net loss attributable to common stockholders was $221.0 million, or $0.76 per basic and diluted share. Adjusted net loss was $4.1 million, or $0.01 per diluted share, on adjusted revenue of $300.4 million. show quote
    “Net loss attributable to common stockholders: $221.0 million • Net loss attributable to common stockholders per basic and diluted share: $0.76 • Adjusted revenue: $300.4 million • Adjusted net loss: $4.1 million • Adjusted net loss per diluted share: $0.01”
    source ↗
  • The non-GAAP measures exclude ChronoScale, the majority-owned accelerated-compute platform that runs the historic cloud services business, although its results are consolidated in the GAAP statements. show quote
    “ChronoScale Holdings Corporation ("ChronoScale"), the Company’s majority-owned accelerated-compute platform, is a public company which owns and operates our historic cloud services business and its results are consolidated into our financial statements, but excluded in the non-GAAP financial measures set forth below.”
    source ↗
  • Adjusted EBITDA was $64.4 million and Net Operating Income was $58.8 million. show quote
    “Adjusted EBITDA: $64.4 million • Net Operating Income: $58.8 million”
    source ↗
  • The release restates the 210 MW, 15-year Delta Forge 2 lease announced on June 8, 2026 with the company's tier-one investment-grade hyperscaler customer, worth approximately $5.2 billion of base-term contracted revenue. show quote
    “As previously announced on June 8, 2026, signed a 210 MW, 15-year lease at Delta Forge 2 with the Company’s tier-one investment grade hyperscaler customer, representing approximately $5.2 billion of base-term contracted revenue.”
    source ↗
  • The second 75 MW phase of Building 2 at Polaris Forge 1 reached Ready for Service on October 1, 2026, bringing operational critical IT load at the campus to 250 MW across two buildings and 10 data halls. Initial operations at Polaris Forge 2 in Harwood are expected to lift delivered critical IT load across the North Dakota campuses to 300 MW by the end of calendar 2026. show quote
    “On October 1, 2026, the Company achieved Ready for Service for the second 75 MW phase of Building 2 at Polaris Forge 1, bringing fully operational critical IT load at the campus to 250 MW across two buildings and 10 data halls. The Company expects initial operations at Polaris Forge 2 in Harwood to increase delivered critical IT load across our North Dakota campuses to 300 MW by the end of calendar 2026”
    source ↗
  • The company closed $1.59 billion of 7.000% Senior Secured Notes due 2031, issued at par, to fund the third HPC building (150 MW) at Polaris Forge 1 and repay the $300 million bridge facility. show quote
    “Closed $1.59 billion of 7.000% Senior Secured Notes due 2031, issued at par through subsidiary APLD ComputeCo 3 LLC, to fund construction of the third HPC building (150 MW) at Polaris Forge 1 and to repay the $300 million bridge facility.”
    source ↗
  • After the quarter, the company secured up to approximately 1 GW of potential power capacity in Finland and signed a Power Purchase Agreement with Base Electron for capacity and energy from an approximately 1,200 MW natural gas-fired facility to be developed in North Dakota. show quote
    “Secured up to approximately 1 GW of potential power capacity in Finland, establishing a strategic foothold in an emerging European AI market. • Entered into a Power Purchase Agreement with Base Electron, for the purchase of capacity and energy from an approximately 1,200 MW natural gas-fired generation facility to be developed by Base Electron in North Dakota.”
    source ↗
  • ChronoScale announced plans with Microsoft for a 50 MW AI compute deployment in North America using NVIDIA GB300 NVL72 systems. show quote
    “ChronoScale announced plans with Microsoft for a 50 MW AI compute deployment in North America featuring NVIDIA GB300 NVL72 systems and liquid cooling.”
    source ↗

From the call

Management framed the year ahead as converting approximately $36 billion of contracted revenue into operating capacity, with over 600 megawatts going into service in the next 12 months against 250 megawatts in the last 12. The CFO's detail qualifies the revenue line: $183.5 million of the $262.6 million of HPC hosting revenue was tenant fit-out services, with $176.1 million of fit-out cost, and base rent was $65.8 million. Funding and pricing are the levers ahead. The last Polaris Forge 1 tranche priced at 7% against 9.25%, three more campuses leased to the same Tier 1 investment-grade tenant still need financing, and management expects expansion leases at materially higher pricing, with lease-rate increases north of 15%.

  • CEO Wes Cummins put contracted revenue at approximately $36 billion across 5 campuses in 3 states. show quote
    “Today, we have approximately $36 billion in contracted revenue across 5 campuses, 3 states and 2 very different geographic regions of the country.”
    source ↗
  • He expects to place over 600 megawatts into service over the next 12 months, against 250 megawatts over the past 12 months. show quote
    “Over the next 12 months, we expect to place over 600 megawatts into service versus the 250 megawatts over the past 12 months.”
    source ↗
  • Most HPC hosting revenue was tenant fit-out services, not rent. Of $262.6 million, $183.5 million was fit-out services, $65.8 million base rent and $13.3 million tenant recoveries. show quote
    “Our HPC hosting business generated $262.6 million of revenue, consisting of $65.8 million of base rent, $183.5 million of tenant fit-out services and $13.3 million of tenant recoveries.”
    source ↗
  • The fit-out work carried its own cost. Services and other cost of revenues of $245.7 million included $176.1 million for tenant fit-out services in the HPC hosting business. show quote
    “Services and other cost of revenues was $245.7 million, primarily consisting of $176.1 million in tenant fit-out services performed within our HPC hosting business”
    source ↗
  • The CFO called out a $67.5 million non-cash loss on the Babcock & Wilcox warrants and common stock investment, marked to market each quarter. Net loss from continuing operations attributable to common stockholders was $221 million, or $0.76 per share; adjusted net loss was $4.1 million, or $0.01 per diluted share. show quote
    “We also recorded $67.5 million of a noncash loss from the change in fair value of our Babcock & Wilcox warrants and the common stock investment. Both are marked-to-market every quarter as B&W stock price changes. Net loss from continuing operations attributable to common stockholders was $221 million or $0.76 per share. Adjusted net loss was $4.1 million or $0.01 per diluted share.”
    source ↗
  • The final Polaris Forge 1 tranche priced at 7%, against a 9.25% coupon on the first Polaris Forge 1 notes. The CFO credited the credit enhancements secured for CoreWeave and growing investor confidence. show quote
    “Our first Polaris Forge 1 related notes placed last year carry a 9.25% coupon. This tranche placed -- priced at 7%. We believe the pricing reflects the credit enhancements we secured for CoreWeave earlier this year and growing investor confidence in our platform.”
    source ↗
  • The next campuses to finance are Polaris Forge 3, Delta Forge 1 and Delta Forge 2, all leased to the same Tier 1 investment-grade hyperscaler under 15-year take-or-pay leases. show quote
    “Looking ahead, the next campuses we need to finance are Polaris Forge 3, Delta Forge 1 and Delta Forge 2. All of these are leased to the same Tier 1 investment-grade hyperscaler under 15-year take-or-pay leases.”
    source ↗
  • The quarter ended with approximately $2.9 billion of cash and equivalents plus $0.7 billion of restricted cash, against approximately $6.4 billion of debt, more than 80% of which is not due until fiscal 2031 or later. show quote
    “We ended the quarter with approximately $2.9 billion in cash and cash equivalents plus $0.7 billion of restricted cash and approximately -- against approximately $6.4 billion of debt. Note, more than 80% of that principal does not come due until fiscal 2031 or later.”
    source ↗
  • Management expects approximately 250 megawatts of expansion leases to be signed by calendar year-end at materially higher pricing than prior leases. show quote
    “We currently expect approximately 250 megawatts of expansion leases to be executed by calendar year-end at materially higher pricing compared to prior leases.”
    source ↗
  • Asked to define premium pricing, Cummins pointed to lease-rate increases north of 15%, possibly with longer lease durations, without committing to a number. show quote
    “I don't want to pin that, but you can think of definitely north of 15% plus increases on the lease rate, but also could include longer duration on the leases.”
    source ↗
  • On the target of 3.5 to 4 gigawatts by the end of 2030, Cummins said the power is in the pipeline, including Base Electron capacity arriving in 2030, and framed the target as a question of how far the company can ramp build and delivery. show quote
    “it was 3.5 to 4 gigawatts that we talked about by the end of 2030. So that's really from a power perspective, we have power in the power pipeline. Some of that includes the additional capacity from Base Electron that comes on in 2030. But from a power perspective, we believe we have that in the pipeline. This was really an exercise around how much more can we ramp up our build and delivery.”