IREN — 2026Q3 財報

公布於 2026-08-27

每股盈餘 -$0.25,預期 -$0.46 — 優於預期

次一交易日 -12.5%(收盤 2026-08-27 → 2026-08-28)

來源

8-K 文件 ↗

綜述

IREN's fiscal year to June 30, 2026 (reported August 27, 2026) is a transition year priced forward. The release shows AI Cloud Services revenue up ~8x to $128.8m while non-cash impairments of $(638.8)m for the year and $(450.4)m for Q4, mostly on decommissioned Bitcoin mining hardware, weighed on net income, and Q4 Adjusted EBITDA fell on employee and platform costs incurred ahead of the AI Cloud ramp. The forward case rests on contracts: $4bn of contracted ARR for 2026 capacity, $1bn of it operating today, plus a new multi-year contract with a leading frontier AI lab. On the call the CFO put ARR at roughly $0.5 billion at the Q4 exit, $1 billion after Microsoft accepted Horizon 1, and more than $4 billion expected by the end of the December quarter, with a significant amount of the December-quarter capacity arriving late in that quarter, so its reported revenue effect shows up predominantly in the March quarter. Management said 3-year contract pricing is up about 125% since November, guided FY '27 capex to approximately $25 billion to $30 billion, and set that against approximately $14 billion of existing cash and committed GPU financing and prepayments plus a target of roughly $8 billion more.

法說會

法說會網路直播 ↗

會議紀錄 ↗

評述

來自財報

The FY26 release shows the pivot from Bitcoin mining to AI Cloud in both directions: AI Cloud Services revenue up ~8x to $128.8m, against non-cash impairments of $(638.8)m, primarily on decommissioned Bitcoin mining hardware, and a Q4 Adjusted EBITDA decline on costs taken ahead of the ramp, with $4bn of contracted ARR for 2026 capacity ($1bn operating today) and a new multi-year contract with a leading frontier AI lab as the forward anchor.

  • “AI Cloud Services revenue increased ~8x to $128.8m in FY26 (vs FY25 $16.4m)”

    AI Cloud Services revenue grew ~8x to $128.8m in FY26 from $16.4m in FY25.

    來源 ↗
  • “Net income (loss) in FY26 and Q4 FY26 was impacted by non-cash impairments of $(638.8)m and $(450.4)m respectively, primarily related to the decommissioning of Bitcoin mining hardware as sites are converted to support AI Cloud growth”

    Non-cash impairments of $(638.8)m for FY26 and $(450.4)m for Q4 FY26 weighed on net income. The release attributes them mainly to decommissioning Bitcoin mining hardware as sites convert to AI Cloud.

    來源 ↗
  • “Adjusted EBITDA decreased in Q4 FY26 reflecting increased employee related costs and broader platform investment ahead of AI Cloud Services revenue ramp”

    Adjusted EBITDA fell in Q4 FY26. The release puts this down to higher employee costs and wider platform investment made ahead of the AI Cloud Services revenue ramp.

    來源 ↗
  • “Current: $4bn contracted ARR for 2026 capacity; $1bn ARR operating today”

    Contracted annualized run-rate revenue (ARR) for 2026 capacity is $4bn, of which $1bn is operating today.

    來源 ↗
  • “Signed a new multi-year AI Cloud contract with a leading frontier AI lab”

    IREN signed a new multi-year AI Cloud contract with a leading frontier AI lab.

    來源 ↗

來自法說會

Management presented the quarter as a ramp that revenue has not yet caught up with. ARR goes from roughly $0.5 billion at the Q4 exit to more than $4 billion expected by the end of the December quarter, but a significant amount of the December capacity comes on late in that quarter, so its reported revenue effect shows up predominantly in the March quarter. Pricing is up about 125% since November for 3-year contracts. FY '27 capex of approximately $25 billion to $30 billion is set against approximately $14 billion of existing cash and committed GPU financing and prepayments, with roughly $8 billion more targeted.

  • “We exited Q4 at roughly $0.5 billion of ARR. It's $1 billion today following acceptance of Horizon 1 by Microsoft, and that will carry through to the end of the September quarter. And we expect more than $4 billion of ARR by the end of the December quarter, which is already under contract and includes delivery of Horizons 2 through 4.”

    The CFO laid out the ARR path: roughly $0.5 billion at the Q4 exit and $1 billion today after Microsoft accepted Horizon 1. He expects more than $4 billion by the end of the December quarter, which is already under contract and includes delivery of Horizons 2 through 4.

    來源 ↗
  • “A significant amount of the December capacity is expected to come on late in the quarter, so we will see the reported revenue effect come through predominantly in the March quarter.”

    Much of the December-quarter capacity is expected to come online late in that quarter. The reported revenue effect should therefore show up predominantly in the March quarter.

    來源 ↗
  • “So pricing has moved a lot, 3-year contract pricing is up about 125% since November, 5-year is up about 70%. Recent 3-year contracts are pricing in excess of $20 million per megawatt of IT load, paying back the compute investment in around 2 years, while active discussions are now at around $25 million per megawatt.”

    Management said 3-year contract pricing is up about 125% since November and 5-year pricing about 70%. Recent 3-year contracts price above $20 million per megawatt of IT load, paying back the compute investment in around 2 years, and active discussions are at around $25 million per megawatt.

    來源 ↗
  • “For FY '27, we're guiding CapEx of approximately $25 billion to $30 billion. Included in that estimate is delivery of the contracted Microsoft capacity, the other deployments to deliver on 2026 ARR and GPU and data center CapEx for air-cooled deployments scheduled across calendar year 2027.”

    FY '27 capex is guided at approximately $25 billion to $30 billion. It includes the contracted Microsoft capacity, the other deployments behind 2026 ARR, and GPU and data center spend for air-cooled deployments across calendar year 2027.

    來源 ↗
  • “Approximately $14 billion of existing cash and committed GPU financing and prepayments. That includes $7.6 billion of cash on the balance sheet at 30 June, of which $1.7 billion is restricted with most of that $1.7 billion set aside to fund Microsoft GPU CapEx. We're targeting roughly an additional $8 billion of GPU financing and prepayments in support of GPU CapEx requirements, noting the healthy prepayments that we are seeing in recent contracting and the growing market for GPU financing that Dan has spoken to.”

    The CFO cited approximately $14 billion of existing cash plus committed GPU financing and prepayments. That includes $7.6 billion of cash at 30 June, of which $1.7 billion is restricted. He is also targeting roughly an additional $8 billion of GPU financing and prepayments.

    來源 ↗